Dun Laogaire Harbour
Weekly
Title Date Budget
03_Concept Design 25-05-22
04_Preliminary Design 25-05-27
05_Planning Submission Stage 25-05-30
06_Detail Design Stage 25-06-03
T1
T2
T3
T4
Name Cost Hours
User 4 Bertrand Labalette 2700 18.00
User 4 Juan Gil 0 0
User 4 Jagoda Owsianna 0 0
User 4 Bertrand Labalette 2700 18.00
User 4 Juan Gil 0 0
User 4 Jagoda Owsianna 0 0
Estimated Project Costing
99% 20%
All Phase
$2700 OF $435000.00
May 22,2025
May 22,2026
03_Concept Design
$0 OF $15000.00
04_Preliminary Design
$0 OF $250000.00
05_Planning Submission Stage
$0 OF $150000.00
06_Detail Design Stage
$2700 OF $20000.00
Project Details
03_Concept Design
$0 OF $15000.00
May 22,2025
May 22,2026
100%
04_Preliminary Design
$0 OF $250000.00
May 22,2025
May 22,2026
100%
05_Planning Submission Stage
$0 OF $150000.00
May 22,2025
May 22,2026
100%
06_Detail Design Stage
$0 OF $20000.00
May 22,2025
May 22,2026
100%